Google Halts Belgian Data Centre Construction After Permit Order
Google has halted construction on a 50-hectare data centre site in southern Belgium after regional authorities ordered work to stop due to missing planning permission. Regional stakeholders and local authorities face mounting regulatory friction as the dispute over the facility near Charleroi intensifies.
Wallonia Regional Authorities Halt Works Over Unpermitted Building
Wallonia regional authorities instructed the US tech giant to freeze operations at the former mining area after determining that unpermitted construction covered three hectares, which regional spokesman Nicolas Yernaux classified as a major offence.
The mammoth project has faced months of legal litigation following Google‘s bid to alter its original planning permission. The company sought to switch from an initial air-cooling design to a system drawing water directly from the nearby River Sambre. Severe droughts since the spring exacerbated local opposition to drawing river water for industrial cooling, prompting regional officials to reject the application over the summer.
Google challenged that refusal in court, and a judicial hearing is scheduled for January. A Google spokesperson confirmed the company has suspended works in line with local direction while maintaining its commitment to complying with local laws after more than 15 years of operating in Belgium. The dispute highlights growing friction across Europe as technology firms push to expand infrastructure for the artificial intelligence boom.