Dubai‘s Roads and Transport Authority (RTA) will open the last bridge of the World Trade Centre Roundabout Development Project to traffic on Friday, 30 October 2026, completing the project. The 1,000-metre, two-lane bridge carries traffic from Al Majlis Street toward 2nd December Street and can handle about 3,000 vehicles per hour. Travel between the two streets falls from 6 minutes to 1 minute.
The project’s five bridges total 5 km and cost more than Dh696 million. The former roundabout is now an at-grade intersection linking Sheikh Zayed Road with Sheikh Khalifa bin Zayed Street, Sheikh Rashid Street, 2nd December Street, Za’abeel Palace Street and Al Majlis Street. Average delay at the intersection falls from 12 minutes to 90 seconds, and the RTA estimates that more than 500,000 residents and visitors will benefit.
| Route | Bridges | Combined length | Capacity per hour |
|---|---|---|---|
| Sheikh Zayed Road to Sheikh Khalifa bin Zayed Street, toward Deira | 1 | 1,000 m | 3,000 vehicles |
| Sheikh Rashid Street to 2nd December Street | 2 | 2,000 m | Up to 6,000 vehicles |
| Al Majlis Street to 2nd December Street | 2 | 2,000 m | About 6,000 vehicles |
The neighbouring Al Mustaqbal Street Development Project is scheduled for completion in 2027. It includes 1.5 km of bridges and tunnels: three tunnels of 1,100 m combined at the Trade Centre Street intersection and a 400-metre, two-lane bridge. A 3,500-metre section is being widened from three to four lanes in each direction, lifting capacity by 33%, from 9,000 to 12,000 vehicles per hour.
The roundabout works were 65% complete in April 2026, as covered in our report on the DWTC roundabout upgrade.
The RTA’s figure of more than 500,000 beneficiaries and the fall in intersection delay from 12 minutes to 90 seconds are covered in the report on the Trade Centre Roundabout delay cut.