Five Dubai venues are closed for redevelopment and are targeting reopening dates between January and October 2027: Armani Hotel Dubai, the Museum of the Future, The Plaza (formerly Lamcy Plaza), the Burj Al Arab and Barasti.
Armani Hotel Dubai, inside Burj Khalifa, closed on 1 April 2026. Its renovated ballroom and event spaces are due in January 2027 and the full hotel in March 2027. The refurbishment covers rooms and suites, dining venues, the spa, fitness areas, the ballroom and the outdoor spaces.
Jumeirah announced in April 2026 that the Burj Al Arab would close for an 18-month restoration, with guests expected back in October 2027. The programme covers rooms, restaurants and leisure spaces, with interiors designed by architect Tristan Auer.
The Museum of the Future, which opened in February 2022, is temporarily closed while every major exhibition is replaced. The reopening is targeted for the first quarter of 2027.
Lamcy Plaza in Oud Metha, which opened in 1997, is set to reopen as The Plaza in the first or second quarter of 2027, with Azure Properties handling the asset management.
Barasti, open since 1995 at Mina Seyahi, closed in June 2026 after a farewell event on 21 June 2026. It is being rebuilt as a beachfront destination with several zones, with a return planned for 2027.
| Venue | Reopening target |
|---|---|
| Armani Hotel Dubai (ballroom and event spaces) | January 2027 |
| Armani Hotel Dubai (full hotel) | March 2027 |
| Museum of the Future | First quarter of 2027 |
| The Plaza (formerly Lamcy Plaza) | First or second quarter of 2027 |
| Burj Al Arab | October 2027 |
| Barasti | 2027 |